The Gas Turbine Shortage Just Became AI’s Biggest Constraint

요약

Order a heavy-duty gas turbine from GE Vernova today and it won’t arrive until 2031. That’s the company’s actual production schedule, confirmed on its July 22 earnings call, and it’s the fact sitting underneath every AI data center power plan announced in the last two years. It comes up far less often than the announcements do. Goldman Sachs put hard numbers on the demand side in May. U.S. data center power demand climbs from 31 gigawatts in 2025 to 41 GW this year and 66 GW in 2027. Year-over-year capacity additions accelerate…